[Case Study] Duct Insulation Repair - Shortening Construction Time through Thorough Preliminary Investigation!
Duct insulation repair - Shortening construction time through thorough pre-investigation!
At the paper mill, damage occurred to the insulation material of the exhaust duct due to the earthquake. An ISO audit and a factory tour for users are scheduled, and we have been consulted about urgently repairing it before then. Issues: 1. Due to the old equipment, there are no existing drawings or specifications, so measurements must be taken on-site and repairs must be made. 2. There are only about 10 days until the desired completion date for the construction. 3. It is necessary to finish the work in harmony with the surrounding lines.